Projects in Bidding

Project ID Project No. Description Construction Location Bid Date

Projects in Construction

Project ID Project No. Description Construction Location Bid Date
C.P. 2020-46 CP 2020-46 CSAH 46 Subgrade Correction - Mill and Overlay South of CSAH 5/46 intersection  06/08/2020
SAP 011-600-018 SAP 011-600-018 CR 128 & 157 Grading & Aggregate Surfacing CR 157 - TH 200 to 4 miles north...  03/16/2020
SAP 011-605-013 SAP 011-605-013 CSAH 5 Mill & Overlay In city of Longville  06/08/2020
SAP 011-647-006 SAP 011-647-006 CSAH 47 Mill and Overlay CSAH 47 from TH 84 to 0.5 miles...  06/08/2020
Soo Line North ATV Trail Bridge Soo Line North ATV Trail Bridge Soo Line North ATV Trail Bridge   07/13/2020
SP 011-601-026 SP 011-601-026 CSAH 1 Reclaim, Pave & Roundabout   08/10/2020

Construction Status

C.P. 2020-46 Roadwork: CSAH 46 Subgrade Correction - Mill and Overlay - South of CSAH 5/46 intersection Estimated End Date: 10/02/2020
9-21-20 - closure for culvert replacement just south of CSAH 5 will remain in affect until Wednesday, September 23. Mill and Overlay (under traffic) will take place this week.
SAP 011-600-018 Roadwork: CR 128 & 157 Grading & Aggregate Surfacing - CR 157 - TH 200 to 4 miles north and CR 128 - CR 157 to Boy Lake Access Estimated End Date: 09/18/2020
9-21-20 - Contractor is finished with a bulk of the work. There remains a few minor punch list items the contractor will address.
SAP 011-605-013 Roadwork: CSAH 5 Mill & Overlay - In city of Longville Estimated End Date: 07/02/2020
9-21-20 - Mill and overlay will take place today and tomorrow
SAP 011-647-006 Roadwork: CSAH 47 Mill and Overlay - CSAH 47 from TH 84 to 0.5 miles east of CR 174 Estimated End Date: 10/02/2020
9-22-2020 - Culvert site 1 (just East of Wabedo Pass Rd) will be closed starting Wednesday, September 23. There will be 2 separate closures, the contractor is hoping to complete each closure in 1 to 2 days. Culvert site 2 (near the east end of the pavement project) will be closed either Thursday the 24th, Friday the 25th, or a combination of those two days.
SP 011-601-026 Roadwork: CSAH 1 Reclaim, Pave & Roundabout Estimated End Date: 10/30/2020
9-21-20 - Only CSAH 1 west to CSAH 44 North and CSAH 44 South to CSAH 1 East is open during stage 1 of this project.

Planning Projects

These projects are not yet open for bid and are subject to change
Project ID Project No. Description Construction Location Anticipated Bid Date